Yes, but please note that a voltage drop test without a slope is available. To perform the test, set the T2 and T4 parameters to 0 seconds.
The power line abnormality simulation function enables to conduct a preliminary tests only such as a voltage drop and short interruption tests. To fully comply with the standard requirements, our dip simulator and SD009-PCR-LE/WE (power line disturbance immunity testing software) are required.